Neptune Area Sewer (Brown)

      Contractor: SJ Louis Contstruction of Arizona, Inc. LLC awarded on January 27, 2009

Ø      Contract Award Amount: $7,566,755.00 paid to date: $2,016,506.64 (27%)

Ø      Connections to Date: 348 of 745 (47%)

Ø      Main Line Sewer: Tested and accepted 27,820 L.F. out of 56,500 L.F. (49%)

Ø      Contract Completion Date: March 2010

.