Neptune Area Sewer

AMEC issued the Neptune Area 100% submiital to the City.

  • Contractor: SJ Louis Construction of Arizona, LLC awarded on January 27, 2009
  • Contract Award Amount: $7,566,755.00 paid to date: $3,456,727.60 (46%)
  • Connections to Date: 500 of 745 (67%)
  • Main Line Sewer: Tested and accepted 41,487 L.F. out of 56,500 L.F. (73%)
  • Contract Completion Date: March 2010