Canyon Oak Area Sewer

The Canyon Oak Area pre-bid meeting took place September 8th with the bid opening scheduled for September 17th.

  • Contractor: S-2 Contractors, Inc. awarded on November, 2008
  • Contract Award Amount: $8,904,671.00 paid to date: $6,678,877.34 (75%)
  • Connections Completed: 764 of 760 (100%)
  • Main Line Sewer: Tested and accepted 51,966 L.F. out of  54,050 L.F. (96%)
  • Contract Completion Date: December 2009