The Havasupai Area bid opening took place Spetember 3rd with Wagner Construction as the apparent low bidder.

  • Contractor: Wagner Construction, Inc. awarded on September 23, 2008
  • Contract Award Amount: $6,734,275.00 paid to date: $6,109,415.41 (85%)
  • Connections to Date: 730 of 736 (100%)
  • Main Line Sewer: Tested and accepted 45,203.00 L.F. out of 45,673 L.F. 99%)
  • Contract Completion Date: November 2009
  • 2 Approved Change Orders totaling $431,521.21