Indiana Peak Area Sewer (Purple)

  • Contractor: K.R. Swerdfeger Inc. awarded on September 14, 2004
  • Contract Award Amount: $11,977,965; paid to date: $10,253,511.23 (100%)
  • Current Contract Value (Including All Change Orders): $10,253,511.23
  • Connections to Date: 913 of 913 (100%)
  • Main Line Sewer: Tested and accepted 126,396 L.F. out of 126,396 L.F. (100%)
  • Contract Completion Date: October 13, 2005
  • Change Order Status: 1 approved change order for totaling $ 1,724,453.77