El Dorado Area Sewer (Purple)
Contractor:
ERS
, Inc. awarded on
September 21, 2004
Contract Award Amount: $13,086,500.00; paid to date: $12,904,181.00 (100%)
Current Contract Value (Including All Change Orders): $12,904,181.00
Connections Completed: 855 of 855 (100%)
Main Line
Sewer: Tested and accepted 54,839 L.F. out of 54,839 L.F. (100%)
Contract Completion Date:
October 28, 2005
Change Order Status: 1 approved change order for totaling $ 182,319