San Juan Area Sewer (Red)

  • Contractor: S-2 Contractors, Inc. awarded on October 9, 2007
  • Contract Award Amount: $13,008,015.50; paid to date: $12,679,314.22 (98%)
  • Connections to Date: 1,084 of 1,130 (96%)
  • Connections in the last two weeks: 0
  • Main Line Sewer: Tested and accepted 75,298 L.F. out of 76,380 L.F. (99%)
  • Contract Completion Date: November 2008
  • Schedule: Project is complete.

 