Southwind Area Sewers (Purple)

 
  • Contractor: S-2 Contractors, Inc. awarded on May 2004
  • Contract Award Amount: $11,810,439.00; paid to date: $11,128,696.22 (100%)
  • Current Contract Value (Including All Change Orders): $11,128,696.22
  • Connections to Date: 951 of 951 (100%)
  • Main Line Sewer: Tested and accepted 76,143 L.F. out of 76,143 L.F. (100%)
  • Contract Completion Date: July 2005
  • Change Order Status: 1 approved change order for totaling $ 681,742.78

 

 