Palm Tree Area Sewers (Tan)
Contractor: Spirit Underground, LLC awarded on May 26, 2009
Contract Award Amount: $4,724,389.60 paid to date: $1,860,926 (39%)
Connections to Date: 281 of 543 (52%)
Main Line
Sewer: Tested and accepted 20,184 L.F. out of 35,642 L.F. (57%)
Contract Completion Date: February 3, 2010