Aztec Area Sewers (Turquoise)

Contractor: Wagner Place, Inc. awarded on December 12, 2006

Contract Award Amount: $11,770,315; paid to date: $11,770,311.70 (100%)

Current Contract Value (Including All Change Orders): $11,770,311.70

Connections to Date: 998 of 998 (100%)

Main Line Sewer: Tested and accepted 49,653 L.F. out of 49,653 L.F. (100%)

Contract Completion Date: January 2008

Change Order Status: 1 approved change order for Quantities reconciliation totaling $ (3.30)

 

The construction warranty started October 20, 2007 and will end October 20 2008. 